Pittsburgh, PA

ϳԹ was recently named as the Prime Contractor and foundation grouting specialist for the Red Bluff Dam Rehabilitation Project in Orla, Texas.

As part of the rehabilitation effort, the full length of the 87-year-old embankment dam’s foundation will be sealed with a grout curtain in up to three rows along the dam to depths of up to 200 feet.

Photo courtesy of US Bureau of Reclamation

Located five miles north of Orla, Red Bluff Dam was originally constructed across the Pecos River to provide irrigation to farmlands from Red Bluff to the nearby town of Grandfalls.

Due to compositesite geology, the scope of work will include both high and low mobility grouting and microfine injection grouting. The entire grouting program will be monitored and recorded using GROUT I.T., Nicholson’s proprietary automated computerized grouting system.

“This is a challenging project with a very complex geology,” said Luca Barison, Senior Vice President of Pre-Construction for Nicholson’s Major Projects Group. “It is an internal joint venture between two of our groups, Major Projects and our Rocky Mountain Region, who both bring expertise and experience to the project. We’re looking forward to getting Red Bluff Dam rehabilitated for the Owner and the local communities.”

ϳԹwill mobilize to the site by May 2023. The project is expected to be completed by Q3 2025.

ϳԹ was recently named as the Prime Contractor and foundation grouting specialist for the Red Bluff Dam Rehabilitation Project in Orla, Texas.

As part of the rehabilitation effort, the full length of the 87-year-old embankment dam’s foundation will be sealed with a grout curtain in up to three rows along the dam to depths of up to 200 feet.

Photo courtesy of US Bureau of Reclamation

Located five miles north of Orla, Red Bluff Dam was originally constructed across the Pecos River to provide irrigation to farmlands from Red Bluff to the nearby town of Grandfalls.

Due to compositesite geology, the scope of work will include both high and low mobility grouting and microfine injection grouting. The entire grouting program will be monitored and recorded using GROUT I.T., Nicholson’s proprietary automated computerized grouting system.

“This is a challenging project with a very complex geology,” said Luca Barison, Senior Vice President of Pre-Construction for Nicholson’s Major Projects Group. “It is an internal joint venture between two of our groups, Major Projects and our Rocky Mountain Region, who both bring expertise and experience to the project. We’re looking forward to getting Red Bluff Dam rehabilitated for the Owner and the local communities.”

ϳԹwill mobilize to the site by May 2023. The project is expected to be completed by Q3 2025.

About ϳԹ

ϳԹhas been both a leader and an innovator in the geotechnical construction industry for more than 60 years. With regional offices across the country and headquarters located in Pittsburgh, ϳԹis a nationally renowned specialty contractor, offering proven expertise in the design and installation of deep foundation elements, earth retention systems and ground treatment solutions. We pride ourselves on our ability to consistently provide our clients with innovative, high-quality design-build options for projects of varying size and complexity. ϳԹis the North American subsidiary of Soletanche Bachy, one of the world’s leading geotechnical contractors, and is part of a global network of unparalleled geotechnical resources and expertise.

Latest News
Sign Me Up
Thank you! Your submission has been received. Keep your eyes out for our next Drill Down!
Oops! Something went wrong while submitting the form.

The Drill Down.

Sign up to receive our quarterly newsletter and drill down on some of our most interesting projects.